Archive

Author Archive

The New Topfer Theatre: From the Job Trailer

June 24th, 2011

This week at the New ZACH Topfer Theatre jobsite, JE Dunn is continuing to pour concrete beams and columns for the flytower structure, pouring concrete for the lobby slab, and working on electrical and mechanical rough-in.

In the coming weeks JE Dunn will be pouring the lobby slab, preparing for structural steel to begin and installing the masonry for the flytower.

Stay tuned for more updates from the job trailer.

Rachel Delino, Project Engineer

Author: JEDunn Categories: The Topfer Theatre, ZACH Theatre Tags: